Induss Offers Dynea 10 Years Of Fixed Price Supply Security
1. The Challenge: growing needs, limited availability
Since its foundation in 1992, global leader in adhesive and surfacing solutions Dynea (Ghent, Belgium) was licensed to pump up ground water from a local deep source to use as process water in their production cycle.
Over the years, however, environmental considerations limited the allowable volumes of ground water intake from 400,000 m3 in 1992 to 25,000 m3 in 2005. Also, Dynea’s reverse osmosis (RO) installation (for high-quality filtration under pressure) was due for replacement, so they faced a significant investment as well as ever more stringent limits on their use of ground water (potential drinking water) as process water.
As their business development plans involved greater, not smaller, quantities of high-quality water, Dynea challenged Induss to conduct a thorough and independent feasibility study of alternative water sources and all consequent issues of licensing (permits) and operation.
2. The Answer: outsourcing to Induss
Induss analysed all alternatives and recommended to lower Dynea’s dependence on deep ground water availability through partial outsourcing of the water supply. From the local TMVW pipe network, Induss would be able to guarantee supply security of the desired water qualities and quantities. The technological and infrastructure investment involved would also be made by Induss, saving Dynea a significant non-core cost (CAPEX).
Dynea’s process water needs are now met by surface water from the nearby Moervaart canal (following a considerable investment in ultrafiltration (UF) and reverse osmosis (RO) infrastructure) and by water directly from the TMVW pipe network (requiring only piping into the Dynea plant).
3. The Benefits
Instead of allowing shrinking water availability to compromise their production process or business development plans, Dynea opted for a highly satisfactory and fully transparent partnership with Induss:
1. Dynea avoided a significant non-core investment in technology and infrastructure.
2. A 10-year supply contract was negotiated at a transparent water price.
3. Induss managed the whole project for Dynea, from proposal to on-site and off-site infrastructure development.
4. New installations were built and put into operation with very short lead-times.
"I am certain of the water quality I need when I need it, and at a transparent price for 10 years."